Updated 17 November 2026. Compiled by the Dholera Guide desk from the sources listed at the end of this page.
Dholera SIR is built by public bodies, not by plot developers. DSIRDA plans and permits, DICDL builds the shared infrastructure, NICDC funds it for the central government, NHAI built the expressway, DIACL is building the airport, GPCL leads the solar park and Railways will build the rail line. Private developers sell plots inside it. Checked 17 November 2026.
| Body | What it is | What it builds or controls | Status and source tier |
|---|---|---|---|
| Dholera SIR Development Authority (DSIRDA) | The statutory planning and land authority for the region, set up under the Gujarat Special Investment Region Act, 2009. | Sanctions the town planning schemes and the development plan, and gives development permissions. It plans and regulates the land; it is not the main builder. | Official. Fact pack and the authority's own portal. |
| Dholera Industrial City Development Limited (DICDL) | The company that builds the city's shared infrastructure. Incorporated 28 January 2016; Gujarat government holds 51 per cent and the central government's NICDC Trust 49 per cent. | Trunk roads, utilities, water and the public facilities in the Activation Area, through contractors it awards work to (see the awards below). | Official. DICDL annual report 2024-25. |
| National Industrial Corridor Development Corporation (NICDC) | The central government's nodal agency for the industrial corridors, including the Delhi-Mumbai Industrial Corridor of which Dholera is a node. | Funds and supports the Activation Area works. Its progress report dated 30 June 2026 records approved infrastructure packages of Rs 2,784.83 crore across five packages, matching equity of the same amount released, and 48.31 sq km transferred to DICDL. | Official. NICDC progress report, 30 June 2026. |
| National Highways Authority of India (NHAI) | The central agency that built the Ahmedabad-Dholera Expressway. | A 109 km four-lane access-controlled road, expandable to eight lanes. Reported opened on 31 March 2026. | Road length official; opening date reported. |
| Dholera International Airport Company Limited (DIACL) | The airport company. Airports Authority of India holds 51 per cent, Gujarat 33 per cent and NICDC 16 per cent. | A 3,200 m runway, terminal and tower. The airport is not open. Officials said on 16 October 2026 that operations are expected by the end of 2026; no aerodrome licence or airline schedule has been reported. | Shareholding official; timeline reported. |
| Gujarat Power Corporation Limited (GPCL) | The state company that is the agency for the Dholera Ultra-Mega Solar Power Park. | Phase I is sanctioned at 1,000 MW. The Central Electricity Authority's report as of September 2025 gives about 300 MW commissioned; the 5,000 MW figure is a long-range target, not installed capacity. | Official, Central Electricity Authority, September 2025. |
| Union Cabinet and Indian Railways | The approving body and the operator of the planned Ahmedabad-Dholera semi-high-speed rail line. | About 134 km of double line at about Rs 20,667 crore, approved on 13 May 2026, with completion targeted up to 2030-31. No construction start has been reported. | Official approval, PIB release 2260624. |
Download this table (CSV). Last checked 17 November 2026. Free to quote with a link to this page.
When people ask who is developing Dholera, they often mean two different groups. The first group is public: the authority that plans the land, the company that builds roads, water and public buildings, and the central and state agencies that fund and build the expressway, the airport, the solar park and the rail line. The second group is private: developers who register plotted layouts on GujRERA and sell plots to buyers. The two groups do not build the same things. Private builders and developers work alongside these bodies, selling plots inside the city; this page names the public side only.
This page covers the first group. For the second group, the GujRERA register read on 17 November 2026 lists 33 registered projects in Dholera; see the RERA guide for how to read those records.
The DICDL annual report for 2024-25, signed on 10 November 2025, names these works under construction in and around the Activation Area, with the contractor and the award value as printed:
DICDL also sold two plots by e-auction in late 2024, one to GAP Associates for a mixed-use project (14 November 2024) and one to Seksaria Buildcon LLP, in a joint venture with The Amore Banquet, for a three-star hotel (24 December 2024). The authority's tender page lists open tenders for a common effluent treatment plant and a 50 MLD seawater desalination plant, which are not awarded.
The biggest private construction in the region is the semiconductor fab of Tata Electronics, approved by the Union Cabinet on 29 February 2024 with a reported investment of about Rs 91,000 crore. It is a company project inside the SIR, not a public body's build. Officials have said commercial operations are expected in mid-2028. See the fab guide.
This page cannot tell you when a public work will finish, what it costs the buyer or how any of it changes the value of a particular plot. Timelines marked reported come from news reports and officials' statements, not from a completion certificate. Verify GujRERA registration, title and price for the exact plot before you pay.
The Gujarat government holds 51 per cent through the Dholera SIR Development Authority route, and the central government holds 49 per cent through the NICDC Trust. DICDL was incorporated on 28 January 2016 and is the company that builds the shared infrastructure of the region.
No. The city's shared infrastructure is built by DICDL through contractors it awards work to. Private developers register plotted layouts and a few building projects on GujRERA. On the 17 November 2026 read, 33 such projects are registered in Dholera.
The National Highways Authority of India is the agency for the 109 km four-lane expressway. It was reported opened on 31 March 2026. Tolling details for cars were not found in the sources checked on 11 November 2026.
The DICDL annual report 2024-25 names SCC Infrastructure with P. R. Patel and Co., Build Well Engineers, Unique Builders, Aditya Infrabuilcon, Kamnath and Cube Construction Engineering for specific works. Each entry above gives the work, the value and the award date as printed.
No. Officials said on 16 October 2026 that it is expected to be operational by the end of 2026. The Airports Authority of India signed an operation agreement with the airport company about 4 November 2026, and no aerodrome licence or airline schedule had been reported by 11 November 2026.